Building consents · Stats NZ figures to September 2026

Commercial building consents in New Zealand

Councils consented $8.72b of non-residential building work in New Zealand in the year to September 2026, down 3% on the year before. Below: 22,958 commercial consents we hold in New Zealand, searchable and on the map.

Non-residential work$8.72b−3% new and altered
New floor area2,298,056 m²$2,556/m² to build
Consents we hold22,958913 in the last 12 monthsSearch them ↓

Non-residential building work each month

The value of new and altered non-residential buildings consented — offices, shops, factories, warehouses, farm buildings, schools, hospitals — New Zealand, the last five years.

$0$500m$1b$1.5b20222023202420252026October 2021: $823mNovember 2021: $806mDecember 2021: $783mJanuary 2022: $464mFebruary 2022: $716mMarch 2022: $998mApril 2022: $578mMay 2022: $1.04bJune 2022: $655mJuly 2022: $691mAugust 2022: $998mSeptember 2022: $833mOctober 2022: $825mNovember 2022: $830mDecember 2022: $856mJanuary 2023: $475mFebruary 2023: $835mMarch 2023: $1.04bApril 2023: $665mMay 2023: $1.23bJune 2023: $764mJuly 2023: $823mAugust 2023: $751mSeptember 2023: $659mOctober 2023: $738mNovember 2023: $763mDecember 2023: $647mJanuary 2024: $963mFebruary 2024: $864mMarch 2024: $680mApril 2024: $739mMay 2024: $850mJune 2024: $605mJuly 2024: $682mAugust 2024: $953mSeptember 2024: $644mOctober 2024: $935mNovember 2024: $883mDecember 2024: $507mJanuary 2025: $581mFebruary 2025: $734mMarch 2025: $751mApril 2025: $768mMay 2025: $979mJune 2025: $624mJuly 2025: $689mAugust 2025: $596mSeptember 2025: $947mOctober 2025: $872mNovember 2025: $789mDecember 2025: $584mJanuary 2026: $607mFebruary 2026: $693mMarch 2026: $862mApril 2026: $655mMay 2026: $789mJune 2026: $701mJuly 2026: $730mAugust 2026: $658mSeptember 2026: $776m

What is being built

Non-residential building work consented in the year to September 2026, by type: the value of new and altered work, new floor area, and what new floor area cost to build per square metre.

  1. Offices$1.46b

    180 buildings · 121,807 m² new floor area · $4,740/m² new · −21% on the year before

  2. Education$1.42b

    273 buildings · 153,571 m² new floor area · $6,444/m² new · +12% on the year before

  3. Warehouses and storage$1.33b

    330 buildings · 637,997 m² new floor area · $1,901/m² new · 0% on the year before

  4. Factories and industrial$972m

    298 buildings · 252,754 m² new floor area · $2,872/m² new · −28% on the year before

  5. Shops, restaurants and bars$806m

    141 buildings · 131,944 m² new floor area · $3,403/m² new · −1% on the year before

  6. Hospitals and health$733m

    94 buildings · 73,398 m² new floor area · $6,196/m² new · −14% on the year before

  7. Social, cultural and religious$729m

    213 buildings · 87,983 m² new floor area · $4,810/m² new · −11% on the year before

  8. Hostels, boarding houses and prisons$532m

    68 buildings · 68,259 m² new floor area · $6,615/m² new · +183% on the year before

  9. Hotels and motels$372m

    88 buildings · 50,941 m² new floor area · $4,612/m² new · +30% on the year before

  10. Farm buildings$371m

    2,010 buildings · 719,402 m² new floor area · $493/m² new · +38% on the year before

Non-residential work since 1991

The value consented each year, in the dollars of the day (not adjusted for inflation).

$0$2.5b$5b$7.5b$10b19952000200520102015202020251991: $852m1992: $1.02b1993: $1.43b1994: $1.79b1995: $2.05b1996: $2.56b1997: $2.27b1998: $2.39b1999: $2.23b2000: $2.38b2001: $2.68b2002: $2.62b2003: $2.82b2004: $3.71b2005: $4.14b2006: $3.94b2007: $4.22b2008: $4.53b2009: $4.53b2010: $3.78b2011: $3.71b2012: $3.91b2013: $4.2b2014: $5.11b2015: $5.92b2016: $6.02b2017: $6.5b2018: $7.09b2019: $7.46b2020: $7.05b2021: $8.39b2022: $9.49b2023: $9.39b2024: $9.31b2025: $8.92b2026 (to Sep 2026): $6.47b

Regions compared

The year to September 2026 against the year before.

RegionNon-residentialChange
Auckland$3.37b+5%
Canterbury$1.34b−14%
Waikato$808m+18%
Wellington$639m−46%
Otago$502m+4%
Bay of Plenty$445m+4%
Manawatu-Whanganui$359m+2%
Hawke's Bay$347m+12%
Northland$246m+52%
Tasman$142m+81%
Southland$137m−36%
Taranaki$128m+25%
Marlborough$127m+122%
Nelson$52.9m−42%
Gisborne$40.3m−9%
West Coast$32.6m−17%

Commercial consents on record in New Zealand

Individual building consents we hold, each on its property: 22,958 from 24 Feb 1993 to 6 Nov 2026. Councils publish their records unevenly, so these are what we have, not every consent issued — for the full count, see the official figures above.

What the work is

Consents in the last five years by the kind of work their description names.

  1. Commercial alterations2,513

    513 in the last 12 months · typically $89k

  2. New commercial buildings1,268

    265 in the last 12 months · typically $750k

  3. Fit-outs429

    93 in the last 12 months · typically $150k

  4. Farm buildings141

    21 in the last 12 months · typically $60k

  5. Relocated buildings111

    18 in the last 12 months · typically $75k

  6. Demolition24

    3 in the last 12 months · typically $300k

Consents on record by month

The last three years. A recent dip is often records still to arrive.

050100150202420252026December 2023: 72January 2024: 61February 2024: 57March 2024: 73April 2024: 60May 2024: 58June 2024: 73July 2024: 103August 2024: 85September 2024: 72October 2024: 91November 2024: 104December 2024: 62January 2025: 50February 2025: 77March 2025: 93April 2025: 73May 2025: 96June 2025: 81July 2025: 94August 2025: 80September 2025: 88October 2025: 83November 2025: 105December 2025: 70January 2026: 61February 2026: 87March 2026: 90April 2026: 107May 2026: 91June 2026: 86July 2026: 90August 2026: 98September 2026: 49October 2026: 43November 2026: 11

Largest in the last 12 months

  1. $46mStage 2 of 2 - Construction of 7 storey hotel - Stage 2 includes Superstructure. Services, Architecture, Facade and Fire 2 Hylton Place, Queenstown
  2. $18.3mErect Building (Stadium) 70 Morgans Road, Glenwood
  3. $14.9mConstruction of a new supermarket building for Woolworths New Zealand Limited (70 Sir Tim Wallis Drive, Three Parks, ) 85-99 Sir Tim Wallis Drive, Wānaka
  4. $13.8mConstruction of 12 residential units (Units 1-5 are two levels, Units 6-12 are three levels) and a common basement carpark of 12 parking spaces under the units 1 5. 2 St Lukes Lane, Queenstown
  5. $13mStage 1- construction of substructure works (slab is excluded) for staff accommodation building with external carparking. 90-94 Thompson Street 90 Thompson Street, Queenstown

22,958 consents

  1. Commercial alterations

    Spec 16 dwelling to be constructed in Advance Build factory and transported to site on separate consent outside the district. Factory Dwelling designed to Very High Wind Zone. Excludes water temp testing and plumbing fixtures leak testing

    2077 State Highway 10, Waipapa · 6 Nov 2026 · EBC-2027-408/0

  2. Commercial alterations

    PIM Only - Remove existing single level building. Construct new two level commercial building

    71 Kerikeri Road, Kerikeri · 6 Nov 2026 · EBC-2027-410/0

  3. Relocated buildings

    Dwelling site consent amendment to add in site works to original consent - newly Factory built dwelling being relocated to site, where foundations, decks, connection to existing services and installation of fire place

    908 Te Ahu Ahu Road, Waimate North · 5 Nov 2026 · EBC-2027-332/0/A

  4. Commercial alterations

    Transportation of factory built modular classrooms to new foundations built on-site. Includes on-site works for deck, walkway and canopy structure including timber and precast stairs, accessible timber ramp and associated site works and connection to services

    12 Lanark Road, Kerikeri · 3 Nov 2026 · EBC-2027-298/0

  5. Fit-outs

    Foundation piles, Storm Water & Wastewater disposal. Internal plumbing fit out + E3 details

    118 Ngapipito Road, Kaikohe · 3 Nov 2026 · EBC-2027-347/0

  6. New commercial buildings$2m

    Erect Shed

    214 Beaconsfield Flat Road, Pareora West · 2 Nov 2026 · BC2026/621

  7. Commercial alterations

    Dwelling - Prefabricated dwelling constructed in Advance Build Factory in Waipapa and transported to site once we have applied for amendment when all the site information has been received

    908 Te Ahu Ahu Road, Waimate North · 2 Nov 2026 · EBC-2027-332/0

  8. Commercial alterations

    Lot 80 - 3-bedroom factory build dwelling with multiple cladding types and mono pitch roof

    , Kaikohe · 2 Nov 2026 · EBC-2027-352/0

  9. Fit-outs

    Installation of machines, plumbing and electrical for laundromat self service retail fitout. No restricted building work

    253 State Highway 10, Cable Bay · 2 Nov 2026 · EBC-2027-384/0

  10. Commercial alterations

    A new 2279 Sqm single storey Commercial Building for a Health Centre, Chemist, Cafe and other health related business

    1526 State Highway 10, Kerikeri · 2 Nov 2026 · EBC-2027-385/0

  11. Commercial alterations

    PIM Only - New Factory built dwelling to be delivered to site - 3 bedrooms, scullery 2 bathrooms, living area, dining, lounge, kitchen and laundry

    32 Bay Heights Drive, Karikari Peninsula · 2 Nov 2026 · EBC-2027-386/0

  12. Commercial alterations

    Dwelling - Prefabricated dwelling constructed in Advance Build Factory in Waipapa and transported to site once we have applied for amendment when all the site information has been received

    15 Akeake Crescent, Karikari Peninsula · 29 Oct 2026 · EBC-2027-336/0

  13. Commercial alterations

    Foundation and subfloor for the 3-bedroom factory build dwelling

    , Kaikohe · 27 Oct 2026 · EBC-2027-371/0

  14. Commercial alterations

    Foundation and subfloor for the 3-bedroom factory build dwelling

    , Kaikohe · 27 Oct 2026 · EBC-2027-372/0

  15. Commercial alterations

    Foundation and subfloor for the 3-bedroom factory build dwelling.

    , Kaikohe · 27 Oct 2026 · EBC-2027-373/0

  16. Commercial alterations

    Foundation and subfloor for the 3-bedroom factory build dwelling

    , Kaikohe · 23 Oct 2026 · EBC-2027-374/0

  17. Commercial alterations

    Lot 2 - Foundation and subfloor for the 2-bedroom factory build dwelling

    , Kaikohe · 22 Oct 2026 · EBC-2027-108/0/A

  18. Commercial alterations

    Lot 4 - Foundation and subfloor for the 2-bedroom factory build dwelling

    , Kaikohe · 22 Oct 2026 · EBC-2027-109/0/A

  19. Commercial alterations

    Lot 6 - Foundation and subfloor for the 2-bedroom factory build dwelling

    , Kaikohe · 22 Oct 2026 · EBC-2027-110/0/A

  20. Commercial alterations

    Lot 1 - Foundation and subfloor for the 2-bedroom factory build dwelling

    , Kaikohe · 22 Oct 2026 · EBC-2027-113/0/A

  21. Commercial alterations$6m

    Building Addition Lactose Dryer and Evaporator Superstructure

    6 Rolleston Road, Clandeboye · 21 Oct 2026 · BC2026/525

  22. Commercial alterations

    Foundation and subfloor for the 2-bedroom factory build dwelling

    , Kaikohe · 21 Oct 2026 · EBC-2027-111/0/A

  23. Commercial alterations

    Lot 5 - 2-bedroom factory build dwelling with gable and roof

    , Kaikohe · 21 Oct 2026 · EBC-2027-366/0

  24. Commercial alterations

    Lot 7 - 2-bedroom factory build dwelling with gable and roof

    , Kaikohe · 21 Oct 2026 · EBC-2027-367/0

  25. Commercial alterations

    Three new detached single-storey retail buildings

    20 Klinac Lane, Waipapa · 20 Oct 2026 · EBC-2026-1042/0

ResidentialCommercial The dots are this page of the list.

Regions in New Zealand

Where the consents we hold are, most in the last 12 months first.

Questions

How many building consents were issued in New Zealand?

In the year to September 2026, Stats NZ counted 41,091 new homes consented in New Zealand, with $20.7b of residential and $8.72b of non-residential building work.

What is a building consent?

Written approval from a council (a building consent authority) that planned building work complies with the Building Code. Most new buildings, additions, structural alterations, fires and plumbing and drainage work need one; some minor work is exempt under Schedule 1 of the Building Act 2004.

Where do these figures come from?

The official counts are Stats NZ’s monthly Building consents issued release (CC BY 4.0), covering every consent every council issues. The individual consents listed are ones we hold from councils’ records and other public sources; they are not a complete list for every council.