Building consents · Stats NZ figures to September 2026

Commercial building consents in Hazelburn

Councils consented $112m of non-residential building work in the Timaru District council area in the year to September 2026, up 78% on the year before. Below: 28 commercial consents we hold in Hazelburn, searchable and on the map.

Non-residential work$112m+78% new and altered
New floor area64,437 m²$1,283/m² to build
Consents we hold28Search them ↓

Stats NZ publishes building consents down to the council, so the official figures on this page are for the Timaru District council area.

Non-residential building work each month

The value of new and altered non-residential buildings consented — offices, shops, factories, warehouses, farm buildings, schools, hospitals — Timaru District, the last five years.

$0$10m$20m$30m$40m20222023202420252026October 2021: $4.8mNovember 2021: $33.5mDecember 2021: $5mJanuary 2022: $4.8mFebruary 2022: $4.5mMarch 2022: $10.1mApril 2022: $3.3mMay 2022: $12.8mJune 2022: $237kJuly 2022: $1mAugust 2022: $2.7mSeptember 2022: $9.3mOctober 2022: $5.1mNovember 2022: $4mDecember 2022: $8.9mJanuary 2023: $1.3mFebruary 2023: $4.2mMarch 2023: $9.9mApril 2023: $2.8mMay 2023: $9.4mJune 2023: $7.6mJuly 2023: $1.5mAugust 2023: $2.1mSeptember 2023: $11.4mOctober 2023: $2.1mNovember 2023: $3.5mDecember 2023: $10.4mJanuary 2024: $353kFebruary 2024: $3.9mMarch 2024: $7.3mApril 2024: $1.8mMay 2024: $17.6mJune 2024: $8mJuly 2024: $6.7mAugust 2024: $19.8mSeptember 2024: $8.5mOctober 2024: $11.7mNovember 2024: $5.8mDecember 2024: $3.4mJanuary 2025: $2mFebruary 2025: $6mMarch 2025: $9.8mApril 2025: $670kMay 2025: $260kJune 2025: $5.5mJuly 2025: $1mAugust 2025: $6mSeptember 2025: $10.5mOctober 2025: $5.7mNovember 2025: $20.7mDecember 2025: $4.7mJanuary 2026: $23.4mFebruary 2026: $27.5mMarch 2026: $1.9mApril 2026: $4.5mMay 2026: $12.1mJune 2026: $1.2mJuly 2026: $3.8mAugust 2026: $2.5mSeptember 2026: $4.2m

What is being built

Non-residential building work consented in the year to September 2026, by type: the value of new and altered work, new floor area, and what new floor area cost to build per square metre.

  1. Social, cultural and religious$48.5m

    3 buildings · 12,611 m² new floor area · $3,786/m² new · +472% on the year before

  2. Factories and industrial$23.4m

    7 buildings · 5,879 m² new floor area · $1,309/m² new · +53% on the year before

  3. Warehouses and storage$18m

    10 buildings · 35,128 m² new floor area · $510/m² new · −12% on the year before

  4. Education$8.8m

    6 buildings · 1,038 m² new floor area · $2,129/m² new · −3% on the year before

  5. Farm buildings$5.1m

    34 buildings · 8,740 m² new floor area · $526/m² new · +57% on the year before

  6. Offices$4.4m

    3 buildings · 408 m² new floor area · $2,819/m² new · +70% on the year before

  7. Shops, restaurants and bars$2m

    +67% on the year before

  8. Hotels and motels$1.8m

    1 building · 633 m² new floor area · $2,204/m² new · −21% on the year before

  9. Hostels, boarding houses and prisons$30k

    −65% on the year before

  10. Hospitals and health$15k

    −87% on the year before

Non-residential work since 1991

The value consented each year, in the dollars of the day (not adjusted for inflation).

$0$25m$50m$75m$100m19952000200520102015202020251991: $11.3m1992: $11.3m1993: $13.3m1994: $19.6m1995: $25.5m1996: $39.9m1997: $24.9m1998: $16.1m1999: $18.7m2000: $30.6m2001: $24.6m2002: $25.8m2003: $23.7m2004: $48.1m2005: $32.9m2006: $38.4m2007: $38m2008: $54.3m2009: $35.3m2010: $50.7m2011: $30.9m2012: $29.4m2013: $49.2m2014: $37.7m2015: $57.6m2016: $43.2m2017: $41.7m2018: $44.6m2019: $38.1m2020: $35.3m2021: $80.9m2022: $66.8m2023: $66.1m2024: $94.9m2025: $73m2026 (to Sep 2026): $80.9m

Commercial consents on record in Hazelburn

Individual building consents we hold, each on its property: 28 from 24 Jan 1994 to 28 Mar 2025. Councils publish their records unevenly, so these are what we have, not every consent issued — for the full count, see the official figures above.

What the work is

Consents in the last five years by the kind of work their description names.

  1. New commercial buildings2

    typically $45k

Consents on record by month

The last three years. A recent dip is often records still to arrive.

00111202420252026December 2023: 0January 2024: 0February 2024: 0March 2024: 0April 2024: 0May 2024: 0June 2024: 0July 2024: 0August 2024: 0September 2024: 0October 2024: 0November 2024: 0December 2024: 0January 2025: 0February 2025: 0March 2025: 1April 2025: 0May 2025: 0June 2025: 0July 2025: 0August 2025: 0September 2025: 0October 2025: 0November 2025: 0December 2025: 0January 2026: 0February 2026: 0March 2026: 0April 2026: 0May 2026: 0June 2026: 0July 2026: 0August 2026: 0September 2026: 0October 2026: 0November 2026: 0

28 consents

  1. New commercial buildings$20k

    Install WWTS for Three Bedroom Dwelling

    · 28 Mar 2025 · BC2025/97

  2. New commercial buildings$70k

    Erect Shed

    373 Henriksen Road · 30 Nov 2021 · BC2021/876

  3. Farm buildings$13k

    Erect Hay Barn

    413 Sterndale Valley Road · 19 Oct 2019 · BC2019/747

  4. New commercial buildings$50k

    Erect Aircraft Hangar

    315 Newton Road · 3 Sep 2019 · BC2019/540

  5. Farm buildings$50k

    Erect Implement Shed

    116 Parr Road · 30 Jun 2018 · BC2018/498

  6. Commercial alterations$20k

    Building Alterations (Shed Extension)

    358 Monument Road · 2 Aug 2017 · BC2017/909

  7. New commercial buildings$32k

    Erect Shed

    48-50 Kerr Road · 20 Feb 2016 · BC2016/52

  8. Farm buildings$20k

    Erect Pole Shed

    350-352 Sterndale Valley Road · 18 Jun 2015 · BC2015/481

  9. New commercial buildings$7,000

    Erect Garage & Erect Three Sheds

    413 Sterndale Valley Road · 22 Jul 2014 · BC2014/645

  10. Farm buildings$19k

    Erect Pole Shed

    69 Newton Road · 13 Jul 2013 · BC2013/656

  11. New commercial buildings$20k

    Erect Two Pole Sheds

    78 Brothers Road · 16 May 2013 · BC2013/286

  12. Farm buildings$840k

    Erect Dairy Shed

    78 Brothers Road · 27 Oct 2012 · BC2012/1008

  13. Farm buildings$13k

    AMEND Erect Pole Shed to Replace Proposed Garage (Not Started)

    413 Sterndale Valley Road · 13 Oct 2012 · BC2008/62790A

  14. New commercial buildings$34k

    Erect Shed (Covered Yards)

    29 Moa Pass Road · 31 May 2012 · BC2012/433

  15. Farm buildings$90k

    Erect Farm Implement Shed

    122 Rockwood Road · 17 Sep 2010 · BC2010/68658

  16. New commercial buildings$30k

    Erect Covered Yards

    535 Three Mile Bush Road · 17 Jun 2010 · BC2010/67723

  17. New commercial buildings$28k

    Erect Two Farm Sheds & Two Silo Bases

    48-50 Kerr Road · 8 Aug 2008 · BC2008/61637

  18. Farm buildings$576k

    Erect Rotary Dairy Shed (69 Newton Road)

    69 Newton Road · 3 Dec 2007 · BC2007/58635

  19. New commercial buildings$29k

    Erect Farm Storage Shed

    1229-1239 Rockwood Road · 15 May 2007 · BC2007/56293

  20. Farm buildings$23k

    Erect Farm Shed

    373 Henriksen Road · 26 Apr 2007 · BC2007/56181

  21. New commercial buildings$8,500

    Erect Implement/Storage Shed

    20 Three Mile Bush Road · 3 May 2005 · BC2005/47587

  22. New commercial buildings$8,000

    Erect Shed

    413 Sterndale Valley Road · 30 Jun 2003 · BC2003/37926

  23. Farm buildings$11k

    Erect Farm Shed

    · 26 Jun 2001 · BC2001/30039

  24. Farm buildings$80k

    New Dairy Shed

    358 Monument Road · 3 Apr 2001 · BC2001/28994

  25. New commercial buildings$10k

    Erect Hayshed

    69 Newton Road · 15 Oct 1996 · BC1996/13720

ResidentialCommercial The dots are this page of the list.

Near Hazelburn

Questions

How many building consents were issued in Hazelburn?

In the year to September 2026, Stats NZ counted 120 new homes consented in the Timaru District council area, with $83.2m of residential and $112m of non-residential building work.

What is a building consent?

Written approval from a council (a building consent authority) that planned building work complies with the Building Code. Most new buildings, additions, structural alterations, fires and plumbing and drainage work need one; some minor work is exempt under Schedule 1 of the Building Act 2004.

Where do these figures come from?

The official counts are Stats NZ’s monthly Building consents issued release (CC BY 4.0), covering every consent every council issues. The individual consents listed are ones we hold from councils’ records and other public sources; they are not a complete list for every council.

Official figures: Stats NZ, Building consents issued, September 2026 release, licensed CC BY 4.0. Values are as declared on the consent, before GST, in the dollars of the day. Recent months are revised as late consents arrive. Council: Timaru District Council.