Building consents · Stats NZ figures to September 2026

Commercial building consents in Dalefield

Councils consented $237m of non-residential building work in the Queenstown-Lakes District council area in the year to September 2026, up 91% on the year before. Below: 13 commercial consents we hold in Dalefield, searchable and on the map.

Non-residential work$237m+91% new and altered
New floor area47,376 m²$4,363/m² to build
Consents we hold13Search them ↓

Stats NZ publishes building consents down to the council, so the official figures on this page are for the Queenstown-Lakes District council area.

Non-residential building work each month

The value of new and altered non-residential buildings consented — offices, shops, factories, warehouses, farm buildings, schools, hospitals — Queenstown-Lakes District, the last five years.

$0$20m$40m$60m$80m20222023202420252026October 2021: $13.6mNovember 2021: $11.8mDecember 2021: $458kJanuary 2022: $9.5mFebruary 2022: $34.3mMarch 2022: $14.7mApril 2022: $9.5mMay 2022: $6.6mJune 2022: $29mJuly 2022: $4.4mAugust 2022: $1.7mSeptember 2022: $2.4mOctober 2022: $14mNovember 2022: $10.8mDecember 2022: $61mJanuary 2023: $9.5mFebruary 2023: $9.8mMarch 2023: $44.3mApril 2023: $9.7mMay 2023: $22.5mJune 2023: $6.2mJuly 2023: $21.1mAugust 2023: $21.5mSeptember 2023: $2mOctober 2023: $17.7mNovember 2023: $70mDecember 2023: $15.2mJanuary 2024: $2.4mFebruary 2024: $8.5mMarch 2024: $4.5mApril 2024: $7.1mMay 2024: $6.4mJune 2024: $10.7mJuly 2024: $10.5mAugust 2024: $4.4mSeptember 2024: $16mOctober 2024: $2.7mNovember 2024: $20.6mDecember 2024: $12.4mJanuary 2025: $3.4mFebruary 2025: $17.9mMarch 2025: $12.9mApril 2025: $15.2mMay 2025: $9.6mJune 2025: $8.9mJuly 2025: $5.8mAugust 2025: $8mSeptember 2025: $6.6mOctober 2025: $3.7mNovember 2025: $19.3mDecember 2025: $15.1mJanuary 2026: $4.6mFebruary 2026: $27.3mMarch 2026: $36.2mApril 2026: $51.4mMay 2026: $11.2mJune 2026: $24.4mJuly 2026: $30.5mAugust 2026: $9.5mSeptember 2026: $4m

What is being built

Non-residential building work consented in the year to September 2026, by type: the value of new and altered work, new floor area, and what new floor area cost to build per square metre.

  1. Hotels and motels$82.4m

    8 buildings · 13,675 m² new floor area · $5,115/m² new · +88% on the year before

  2. Shops, restaurants and bars$57.1m

    15 buildings · 14,795 m² new floor area · $3,258/m² new · +61% on the year before

  3. Social, cultural and religious$25.9m

    7 buildings · 3,497 m² new floor area · $6,822/m² new · +268% on the year before

  4. Hostels, boarding houses and prisons$25.8m

    3 buildings · 6,050 m² new floor area · $4,264/m² new

  5. Offices$20.7m

    6 buildings · 2,766 m² new floor area · $5,998/m² new · +33% on the year before

  6. Education$12m

    5 buildings · 2,611 m² new floor area · $4,475/m² new · +391% on the year before

  7. Factories and industrial$7.2m

    5 buildings · 1,617 m² new floor area · $3,348/m² new · +310% on the year before

  8. Warehouses and storage$4.3m

    3 buildings · 1,774 m² new floor area · $2,430/m² new · +100% on the year before

  9. Farm buildings$892k

    3 buildings · 591 m² new floor area · $1,509/m² new · −75% on the year before

  10. Hospitals and health$800k

    −93% on the year before

Non-residential work since 1991

The value consented each year, in the dollars of the day (not adjusted for inflation).

$0$100m$200m$300m19952000200520102015202020251991: $8.3m1992: $6.1m1993: $18.2m1994: $54.5m1995: $58.4m1996: $24.2m1997: $30.5m1998: $19.8m1999: $29.2m2000: $38.8m2001: $41.2m2002: $35.4m2003: $54.3m2004: $74.2m2005: $61.7m2006: $89.9m2007: $111m2008: $101m2009: $77.4m2010: $38.4m2011: $32.8m2012: $43.3m2013: $24.1m2014: $95.4m2015: $115m2016: $117m2017: $166m2018: $165m2019: $231m2020: $288m2021: $153m2022: $198m2023: $250m2024: $106m2025: $126m2026 (to Sep 2026): $199m

Commercial consents on record in Dalefield

Individual building consents we hold, each on its property: 13 from 29 Feb 2024 to 29 Feb 2024. Councils publish their records unevenly, so these are what we have, not every consent issued — for the full count, see the official figures above.

What the work is

Consents in the last five years by the kind of work their description names.

  1. Commercial alterations1

    typically $250k

Consents on record by month

The last three years. A recent dip is often records still to arrive.

00111202420252026December 2023: 0January 2024: 0February 2024: 1March 2024: 0April 2024: 0May 2024: 0June 2024: 0July 2024: 0August 2024: 0September 2024: 0October 2024: 0November 2024: 0December 2024: 0January 2025: 0February 2025: 0March 2025: 0April 2025: 0May 2025: 0June 2025: 0July 2025: 0August 2025: 0September 2025: 0October 2025: 0November 2025: 0December 2025: 0January 2026: 0February 2026: 0March 2026: 0April 2026: 0May 2026: 0June 2026: 0July 2026: 0August 2026: 0September 2026: 0October 2026: 0November 2026: 0

13 consents

  1. Commercial alterations$250k

    Alterations to existing dwelling - create multi-unit dwelling via alterations to garage and connection of garage to main dwelling - 386 Littles Road, Dalefield

    386 Littles Road · 29 Feb 2024 · BC240034

  2. Farm buildings$92k

    New Glasshouse & Implement Shed

    296 Littles Road · BC010889

  3. Farm buildings$2,500

    Return Tank Pit For Glasshouse System

    296 Littles Road · BC020140

  4. New commercial buildings$20k

    New Workshop Including Pergola

    364 Malaghans Road · BC090767

  5. Commercial alterations$5,000

    Alterations To Workshop

    281A Littles Road · BC131030

  6. New commercial buildings$2,500

    Erect New Garage And Workshop

    370-378 Littles Road · BC930263

  7. Farm buildings$12k

    Erect Implement Shed

    · BC930310

  8. New commercial buildings$11k

    Erect Sleepout, Office & Storage Building.

    44 Tullamore Lane · BC940421

  9. Farm buildings$2,500

    Erect Greenhouse

    90 Fitzpatrick Road · BC950818

  10. Farm buildings$10k

    Additions To Implement Shed

    80 Mountain View Road · BC951281

  11. New commercial buildings$50k

    Erect Workshop

    281A Littles Road · BC980404

  12. New commercial buildings$23k

    Construction Of Workshop

    206 Dalefield Road · BC980665

  13. Commercial alterations$1,000

    Install Fire Appliance In Workshop

    281A Littles Road · BC990636

ResidentialCommercial The dots are this page of the list.

Near Dalefield

Questions

How many building consents were issued in Dalefield?

In the year to September 2026, Stats NZ counted 1,981 new homes consented in the Queenstown-Lakes District council area, with $1.22b of residential and $237m of non-residential building work.

What is a building consent?

Written approval from a council (a building consent authority) that planned building work complies with the Building Code. Most new buildings, additions, structural alterations, fires and plumbing and drainage work need one; some minor work is exempt under Schedule 1 of the Building Act 2004.

Where do these figures come from?

The official counts are Stats NZ’s monthly Building consents issued release (CC BY 4.0), covering every consent every council issues. The individual consents listed are ones we hold from councils’ records and other public sources; they are not a complete list for every council.