Councils consented $142m of non-residential building work in the Tasman District council area in the year to September 2026, up 81% on the year before. Below: 7 commercial consents we hold in Wakefield, searchable and on the map.

Non-residential work$142m+81% new and altered
New floor area37,204 m²$3,355/m² to build
Consents we hold72 in the last 12 monthsSearch them ↓

Stats NZ publishes building consents down to the council, so the official figures on this page are for the Tasman District council area.

Non-residential building work each month

The value of new and altered non-residential buildings consented — offices, shops, factories, warehouses, farm buildings, schools, hospitals — Tasman District, the last five years.

$0$10m$20m$30m$40m20222023202420252026October 2021: $5.9mNovember 2021: $6.2mDecember 2021: $5mJanuary 2022: $6.8mFebruary 2022: $5.4mMarch 2022: $23.6mApril 2022: $9.3mMay 2022: $2.5mJune 2022: $8.2mJuly 2022: $4.8mAugust 2022: $6.9mSeptember 2022: $5.4mOctober 2022: $3.2mNovember 2022: $3.7mDecember 2022: $10.6mJanuary 2023: $3.8mFebruary 2023: $3.5mMarch 2023: $2.3mApril 2023: $3.3mMay 2023: $8.3mJune 2023: $7.2mJuly 2023: $12.5mAugust 2023: $2.7mSeptember 2023: $3.5mOctober 2023: $11.5mNovember 2023: $5.2mDecember 2023: $2.4mJanuary 2024: $8.3mFebruary 2024: $5.8mMarch 2024: $5.2mApril 2024: $1.6mMay 2024: $4.2mJune 2024: $6.1mJuly 2024: $2.9mAugust 2024: $2.7mSeptember 2024: $3mOctober 2024: $27.6mNovember 2024: $5.9mDecember 2024: $17.1mJanuary 2025: $7.2mFebruary 2025: $1.1mMarch 2025: $2.6mApril 2025: $2mMay 2025: $3.3mJune 2025: $3.3mJuly 2025: $1.4mAugust 2025: $2.1mSeptember 2025: $4.9mOctober 2025: $30.2mNovember 2025: $28.9mDecember 2025: $2.9mJanuary 2026: $4.8mFebruary 2026: $7.1mMarch 2026: $22.8mApril 2026: $4.4mMay 2026: $585kJune 2026: $7.3mJuly 2026: $23.7mAugust 2026: $5.8mSeptember 2026: $3.5m

What is being built

Non-residential building work consented in the year to September 2026, by type: the value of new and altered work, new floor area, and what new floor area cost to build per square metre.

  1. Shops, restaurants and bars$45.8m

    7 buildings · 9,720 m² new floor area · $4,131/m² new · +25% on the year before

  2. Hospitals and health$27.8m

    2 buildings · 4,226 m² new floor area · $6,425/m² new · +4320% on the year before

  3. Education$20.6m

    1 building · 1,160 m² new floor area · $13,793/m² new · +458% on the year before

  4. Factories and industrial$15m

    6 buildings · 7,502 m² new floor area · $1,882/m² new · −9% on the year before

  5. Social, cultural and religious$9.3m

    2 buildings · 1,979 m² new floor area · $4,118/m² new · +15% on the year before

  6. Offices$7.5m

    3 buildings · 776 m² new floor area · $5,528/m² new · +126% on the year before

  7. Farm buildings$5.7m

    19 buildings · 8,768 m² new floor area · $575/m² new · +185% on the year before

  8. Warehouses and storage$5.1m

    3 buildings · 1,711 m² new floor area · $2,981/m² new · −2% on the year before

  9. Hostels, boarding houses and prisons$4.6m

    3 buildings · 1,230 m² new floor area · $3,541/m² new · +151% on the year before

  10. Hotels and motels$610k

    1 building · 132 m² new floor area · $3,485/m² new · +4% on the year before

Non-residential work since 1991

The value consented each year, in the dollars of the day (not adjusted for inflation).

$0$25m$50m$75m$100m19952000200520102015202020251991: $6.8m1992: $11.4m1993: $12.2m1994: $15m1995: $12.9m1996: $29.6m1997: $18.2m1998: $16.8m1999: $13.3m2000: $18.6m2001: $33.3m2002: $24.7m2003: $32.8m2004: $35.7m2005: $41.8m2006: $20.3m2007: $34.2m2008: $26.4m2009: $27.7m2010: $29.5m2011: $22.7m2012: $29.7m2013: $32.1m2014: $29.2m2015: $23.5m2016: $32.1m2017: $31.9m2018: $49.2m2019: $40.2m2020: $62.7m2021: $56.9m2022: $90.3m2023: $66.2m2024: $90.4m2025: $89.8m2026 (to Sep 2026): $80m

Commercial consents on record in Wakefield

Individual building consents we hold, each on its property: 7 from 1 May 2021 to 1 Aug 2026. Councils publish their records unevenly, so these are what we have, not every consent issued — for the full count, see the official figures above.

What the work is

Consents in the last five years by the kind of work their description names.

  1. Commercial alterations4

    1 in the last 12 months · typically $58k

  2. Fit-outs1

    1 in the last 12 months · typically $90k

Consents on record by month

The last three years. A recent dip is often records still to arrive.

00111202420252026December 2023: 0January 2024: 0February 2024: 0March 2024: 0April 2024: 0May 2024: 0June 2024: 0July 2024: 1August 2024: 0September 2024: 0October 2024: 0November 2024: 0December 2024: 0January 2025: 0February 2025: 0March 2025: 0April 2025: 0May 2025: 0June 2025: 0July 2025: 0August 2025: 0September 2025: 0October 2025: 1November 2025: 0December 2025: 0January 2026: 0February 2026: 0March 2026: 0April 2026: 0May 2026: 0June 2026: 1July 2026: 0August 2026: 1September 2026: 0October 2026: 0November 2026: 0

Largest in the last 12 months

  1. $125kEnclose porch, alt internal layout, install ensuite, sink & wall lining to basement office, insulate exterior walls of dwg 19 Harcourt Place, Wakefield
  2. $90kRbw. Change of use - basement storage area changed to accommodation. Basement internal fit-out. 80% of the basement will be used as accommodation for transient use only & another 20% for their stora 79 Wakefield-Kohatu Highway, Wakefield

7 consents

  1. Commercial alterations$125k

    Enclose porch, alt internal layout, install ensuite, sink & wall lining to basement office, insulate exterior walls of dwg

    19 Harcourt Place, Wakefield · 1 Aug 2026 · 1001/26

  2. Fit-outs$90k

    Rbw. Change of use - basement storage area changed to accommodation. Basement internal fit-out. 80% of the basement will be used as accommodation for transient use only & another 20% for their stora

    79 Wakefield-Kohatu Highway, Wakefield · 1 Jun 2026 · BCO10399752

  3. Commercial alterations$50k

    Construct a gge with workshop

    27 Whiting Drive, Wakefield · 1 Oct 2025 · 25/0803

  4. Commercial alterations$65k

    Replace gge & re-clad existing workshop

    29 Pitfure Road, Wakefield · 1 Jul 2024 · 24/0487

  5. Commercial alterations$9,000

    Add of bathrm to gge/workshop

    22 Moore Road, Wakefield · 1 Jul 2022 · 22/0770

  6. Commercial alterations$51k

    Construct sleepout & office

    203 Whitby Road, Wakefield · 1 Sep 2021 · 21/0552

  7. Commercial alterations$49k

    Construct detached workshop

    18 Totara Street, Tapawera · 1 May 2021 · 21/0533

ResidentialCommercial The dots are this page of the list.

Suburbs in Wakefield

Where the consents we hold are, most in the last 12 months first.

Questions

How many building consents were issued in Wakefield?

In the year to September 2026, Stats NZ counted 280 new homes consented in the Tasman District council area, with $166m of residential and $142m of non-residential building work.

What is a building consent?

Written approval from a council (a building consent authority) that planned building work complies with the Building Code. Most new buildings, additions, structural alterations, fires and plumbing and drainage work need one; some minor work is exempt under Schedule 1 of the Building Act 2004.

Where do these figures come from?

The official counts are Stats NZ’s monthly Building consents issued release (CC BY 4.0), covering every consent every council issues. The individual consents listed are ones we hold from councils’ records and other public sources; they are not a complete list for every council.

Official figures: Stats NZ, Building consents issued, September 2026 release, licensed CC BY 4.0. Values are as declared on the consent, before GST, in the dollars of the day. Recent months are revised as late consents arrive. Council: Tasman District Council.